Monitoring of subprojects is carried out in Namangan region

During the period of May 20-24 of the current year in Namangan region, subprojects within the framework of the Rural Infrastructure Development Project are being monitored. Monitoring affects 67 mahallas in five districts of the region.

The process is being led by Shokirjon Ibragimov, Chief Engineer of the JPIU, in collaboration with other experts of the technical supervision team and Qishloq Engineers of the Facilitating Partner (“CEED/Rhythm Plus”).

During visits to construction sites, specialists study design and estimate documentation, contractors’ compliance with building codes and regulations, created conditions to for ensuring safety at sites, as well ensuring the required quality and timeliness of works performed.

Based on the monitoring, appropriate instructions are provided to correct identified deficiencies and additional recommendations are issued.