Application of funds

INFORMATION on the work carried out under the Resolution of the President of the Republic of Uzbekistan dated November 25, 2020 No. PQ-4898 "On measures to implement «Rural Infrastructure Development» Project with the participation of the International Development Association of the World Bank and the Asian Infrastructure Investment Bank"

01/12/2024

thousand USD

# Project Components The total cost of the project Disbursed funds as of January 1, 2024 Application of funds in 2024
Plan Fact
SUMMARY: 182,000 63,270.0 50,000.0 28,664.2
including
1 Subcomponent 1a: demand-driven investments in basic infrastructure and services. 164,000 58,027.0 48,100.0 27,361.0
2 Subcomponent 1b: Local Governance Capacity support, Communication and Public Outreach, Citizen Engagement. 11,700 3,012.0 1,100.0 648.1
3 Component 2: Project Management, Monitoring and Evaluation, and Capacity Building. 6,300 2,231.0 800.0 655.1

Project implementation period: 2020–2026.

Subprojects in numbers
# Area name Rural development plan (QDP) Chosen subproject number School Kindergarten Water supply & sanitation Drainage system Road Bridge Energy Hospital
Number KM Number KM Number KM Number KM
SUMMARY: 176 239 28 15 105 1640.7 1 3 55 606.1 3 29 552.25 3
1 Andijan 36 36 1 10 96.6 25 330
1.1 Pakhtaobod 16 16 1 7 62.3 8 88.4
1.2 Markhamat 10 10 1 12 9 153
1.3 Bulokboshi 6 6 6 73
1.4 Buston 2 2 2 15.8
1.4 Ulugnar 2 2 2 22.3
2 Fergana 28 28 4 1 17 498 5 32 1 15.2
2.1 Koshtepa 13 13 12 382 1 15.2
2.2 Yozyovon 5 5 1 1 11 3 17.3
2.3 Furkat 5 5 4 105 1 10
2.4 Sokh 5 5 3 1 1 4.7
3 Namangan 67 67 4 2 56 625.5 5 35.7
3.1 Yangikurgan 18 18 1 17 127.3
3.2 Pop 18 18 2 1 14 127.5 1 8.7
3.3 Chust 13 13 1 1 9 118.5 2 14
3.4 Chartak 10 10 10 216
3.5 Mingbulak 8 8 6 36.2 2 13
4 Jizzakh 28 67 4 21 404.6 14 162.5 1 25 501.4 2
4.1 Bakhmal 9 21 8 187.8 4 52.7 1 7 89.2
4.2 Zomin 12 38 4 12 216.4 9 76.6 12 246.3 2
4.3 Forish 6 7 1 33.2 6 165.9
4.4 Yangiobod 1 1 1 0.4
5 Syrdarya 17 41 15 12 1 16 1 3 6 45.9 2 3 35.7 1
4.1 Boyovut 12 31 12 10 4 25.66 2 2 25.7 1
4.2 Sardoba 1 2 1 16 1 10
4.3 Khovos 4 8 3 2 1 3 2 20.2

Project implementation period: 2020–2026.